|
PNE 0296.55 - Lighting Rehabilitation
$1M Projected completed Phase V is the final phase of an overall
program at Northeast Philadelphia Airport to upgrade the airfield electrical
systems. The work completed is the completion of runway edge lighting,
modernization of NAVAIDS including PAPI's, and enlarging the fuel storage tank
for the standby generator set.
PHL 1346.14/15/16/17 - Terminal A East
Renovations (Alterations) $12.5M Projected completed This is one
phase of the overall Terminal A East Improvement Project, which consists of
various improvements to the Terminal A East building and concourse to make it
fully compatible with the newer, adjacent Terminal A West. Work already
completed includes creation of a new eight-lane security checkpoint replacing
the existing five lane checkpoint, upgrade of fire alarm and fire protection
systems and refurbishment of ticketing area and concourse, including finishes
and systems, and a childrens play area. Remaining work is the next phase of the
Automatic Vehicle Identification system (AVI) to be installed.
PHL 1385.14/15 - Taxiway Reconstruction
Program - Phase I $6M Projected completed Phase I includes the
reconstruction of Taxiways M, N, S1 and S, primarily removal and replacement of
pavement and associated lighting and NAVAIDS.
PHL 1278.44 - Taxiway J and Cargo Ramp
Reconstruction - Phase IV $6.5M Projected completed This Phase IV
is the Cargo Apron Reconstruction Project. The section of the cargo apron to be
reconstructed is immediately south and adjacent to cargo buildings C-6, C-4 and
C-3, approximately 52,000 SY. In this same cargo apron area, Taxiway J was
reconstructed in 2000 (Phase I) and the portion of the apron immediately north
of that was completed in 2002 (Phase II). The portions directly south of cargo
building C-7 and C-2 (Phase III) are recently completed.
PHL 1331.24/25 - Facility Management
System - MUFIDS Phase II $7.5M Projected completion July 2008 The
Airport maintains and operates a Flight Information Display System (FIDS) that
provides information about the status of each flight for every air carrier on
over 600 monitors located throughout the terminal complex. Under the first
phase, new monitors have been installed in the new Terminal A-West. The new
monitors are 42" flat panel type. In Terminals A East through F, new
communications hardware and software were installed under Phase I to provide
detailed gate utilization data, and will allow for the installation of 413 LCD
flat panel monitors under the second phase, which shall commence shortly.
Twenty one of the new monitors will be dedicated to visual paging.
PHL 1401.14/15/16 - Runway 17-35
Extension Project (Phase I: Landside) $31M Projected completion May
2008 PHL 1401.24/25 (Phase II: Embankment) $5M Projected completion
November 2007 PHL 1401.34/35 - (Phase III: Airside) $29M Projected
completion March 2009 In an effort to alleviate existing and forecast
delays, the City of Philadelphia will complete major improvements to increase
airfield capacity at PHL. The Runway 17-35 Extension Project will provide a
short-term delay reduction. The major components of the entire project include:
- Extension of Runway
17-35;
- Extension of parallel
Taxiways D and E;
- Construction of a High
Speed Taxiway for Runway 35 landings exiting to Taxiway E;
- Construction of an
Aircraft Holding Apron at Runway 35 end;
- Relocation of Airside
Perimeter Service Roads at Runway 17 and Runway 35 ends;
- Installation of High
Intensity Runway Lighting (HIRL) and Medium Intensity Taxiway Lighting
(MITL);
- Modifications to
airfield signs;
- Substantial
relocation/modification of navigational aids (NAVAIDS):
- Demolition of existing
Taxiways D2 and E2;
- Modifications to
existing Economy Parking Lot;
- Re-designation of
existing State Route (SR) 291 north of Airport;
- Modifications to
Bartram Avenue from the SR 291 intersection to Island Ave., SR 291 and I-95
ramps;
- Demolition of SR 291
at Runway 17 extension work area;
- Construction of
Landside Service Road adjacent to I-95 right-of-way limit;
- Associated drainage,
grading and utility relocations/modifications.
The first phase (IG), which allowed for the redesignation of Route 291, is
complete. The remaining phases I, II and III are in progress.
PHL 1247.14/15/16/17 - Terminals D/E Connector Building Phase IA $20M
Projected completion November 2007 PHL 1247.24/25/26/27/2B/2E -
Terminals D/E Connector Building Phase IB $91M Projected completion
December 2008 PHL 1247.34/35/36/37/3E - Term. D/E Ticketing Renovations &
Bag Claim Phase II $91M Projected completion February 2010 This
project consists of a new multi-level connector building between Terminals D
and E, a 50,000 SF addition to the Terminal E concourse, a 9,000 SF connector
building between Bag Claims D and E, and various renovations to areas within
the two terminals and the adjacent Thermal Plant.
Phases IA and IB are
the new multi-level connector building between Terminals D and E. The first
level will house a new baggage make-up area, which would replace the existing
areas in each of the terminals. This area will also contain an Explosive
Detection System (EDS), to be operated by the TSA as part of an in-line baggage
screening system. The second level will be a 14-lane passenger security
screening area serving both terminals, and the third level will house Division
of Aviation offices and have space for an airline club. The Phase IA portion
that is finishing up, consisted of site work, building foundations, utility
relocation and structural steel placement for the connector building. Work on
Phase IB has commenced in July 2007 and will complete the connector building.
The modifications to existing terminal buildings will include an
increase of 23 ticket counter positions with larger queuing spaces, increased
public circulation, new concessions and other tenant spaces. The Terminal E
Concourse will be expanded with the construction of a 2-level addition at the
end of the concourse. Airline Operations space will be at ground level. The
second level will provide hold rooms, concessions, rest rooms and operations
space to accommodate three new gates and four relocated gates. The Bag Claim
buildings for Terminals D & E will be connected with a one story addition
that will contain two new baggage carousels.
|